“We’ve
identified sections of the roadway that are in immediate need of rehabilitation
along Centre Street and hope to have the work completed over the next couple of
weekends,” says Chris McGeachy, spokesperson for Roads.
Due to the scope of the work, crews will
have to close various lanes which will have an impact on traffic.
“To maximize efficiency, we will begin work
on localized sections of the northbound lanes this weekend, weather permitting,
and then turn around and head southbound the following weekend,” adds McGeachy.
The first weekend closures will be focused
on the northbound lanes, with milling work starting on Friday, Sept. 23.
- Milling on Centre Street N will take place on Friday, Sept. 23 from 9 a.m. to 2 p.m. from 7 Avenue to 16 Avenue. The road will be reduced to a single lane in each direction at various areas throughout this closure. Police will be onsite to detour traffic when milling work occurs in the intersections
- Milling and paving work will occur from 6:30 a.m. to 9 p.m. on Saturday, Sept. 24 and Sunday, Sept. 25. During these times, the northbound lanes of Centre Street will be closed and two way traffic will be in place in the southbound lanes between 7 Avenue and Beddington Boulevard N.E. Motorists are advised to use alternate routes when possible.
While the schedule for the following
weekend (Sept. 30 – Oct. 2) has not been finalized, motorist should expect to
see similar closures in the southbound lanes during that time.
The City of Calgary’s Surface Overlay
program helps rejuvenate our transportation network and provide a smooth
surface for road users. For more information on paving, visit Calgary.ca/paving.